Wadsworth Construction is based in Draper.
According to UDOT, the total project value is $97.5 million.
The actual construction portion of the project was valued at approximately $65 million. Right of way purchases, engineering, design and other pre-construction costs totaled an additional $32.5 million. Wadsworth’s bid to build the construction portion of the interchange project is $60.9 million.
This bid is to build the entire interchange, including the structure over the UPRR/UTA rail corridor and a system of roads connecting this structure to Gentile Street.
It is expected that a notice to proceed on this project will be received sometime near the end of July. Initial pre-construction efforts will begin within weeks of that notice. Right of way purchases and relocations are presently approaching their final stages.